Cycle Time Calculator

Minutes per unit from a shift length and how many units were finished.

 

 

Min / unit

About this calculator

Use this calculator on a line or a desk when you know elapsed minutes and pieces completed.

Cycle time is minutes ÷ units. 480 minutes and 40 units is 12 minutes each. Lead time (wait plus process) is a different clock. Takt uses customer demand instead of pieces finished.

Minutes: Available or elapsed minutes.

Units: How many pieces finished, not zero.

Min / unit: Average cycle time.