PERT Estimate Calculator

Expected time (o + 4m + p) / 6 and a (p − o) / 6 spread.

 

 

 

Expected
Spread

About this calculator

Use this calculator for a three-point PERT estimate. Enter optimistic, most likely, and pessimistic durations in the same unit (days, hours, whatever you use).

Expected te = (o + 4m + p) / 6. Spread sd = (p − o) / 6. Optimistic 4, most likely 6, pessimistic 12 gives 6.667 expected and 1.333 spread. Paths in a network are extra; this is one activity.

Optimistic: Best case.

Most likely: Usual case.

Pessimistic: Worst case.

Expected: Weighted mean.

Spread: (p − o) / 6, a PERT standard-deviation sketch.